Projects and Works

Introduction

The Capital Works Program has been developed to meet anticipated community infrastructure needs and the future development of the Town to align with the strategic plan, driven by population growth, requirements of the community and asset management.  These works include footpath replacement, traffic management treatments and road re-sheeting works among other minor capital works.

Jump to:

Upcoming Projects
Underground Power Project
nbn
Rollout
Maintenance

Upcoming Projects 

Footpath Reconstruction - Mofflin Avenue (north side)

The footpath reconstruction project for the north side of Moffline Avenue is scheduled to commence on Monday 5 August 2019.  The goal is to complete these works by Friday 9 August 2019, weather permitting.

If you have any queries regarding these works, please contact us.

Footpath Reconstruction - Garden Street (south south between Central Avenue & Devon Road)

The footpath reconstruction project for the above is scheduled to commence on Monday 5 August 2019.  The goal is to complete the major works by Friday 9 August 2019, weather permitting.

If you have any queries rgarding these works, please contact us.  
 

Road Rehabilitation Project 2019-20 - Goldsmith Road (between Loton Road & Stone Road)


The above project is scheduled to commence on Monday 5 August 2019.  The goal is to complete the works by Friday 9 August, weather and contractor availability permitting.

If you ahve any queries regarding these works, please contact us.

 

Underground Power Project

The undergrounding of power to the final pocket of the Town of Claremont commenced in May 2018. The project will run for approximately 14 months with a planned completion around July 2019, weather and contractor conditions permitting. 
Please click here to view the Project Start-Up Newsletter. Below is a map of zone areas as well as an up-to-date table of estimated start and completion dates for each zone (updated 15 February 2019).


Please note the Estimated Start and Estimated Completion dates in the table below have changed from those originally publicised in the 2018 Project Start Up information pack dated 30 April 2018. 
map.png

  Estimated Start Date Estimated Completion Date
Zone 1 May 2018 February 2019 (complete)
Zone 2 June 2018 May 2019 (complete)
Zone 3 June 2018 May 2019
Zone 4 October 2018 June 2019
Zone 5 November 2018 June 2019
Zone 6 January 2019 June 2019
Zone 7 February 2019 July 2019
Zone 8 February 2019 July 2019
Zone 9 August 2018 April 2019 (complete)
Project Completion   July 2019


Last updated 15 May 2019. 


Please click here to view the Frequently Asked Questions. 

To view a map of the high voltage transmission powerlines (66v and 132v) that will not be removed, please click here.

Underground-Parking.jpg


Maintenance

To report a problem

Roads signs line markings and traffic signals are serviced by Main Roads WA.